This document is a summary of a printed document. The printed document may also contain charts and photographs which are not reproduced in this electronic version. If you require the printed version of this document, contact the Freedom of Information Act Officer, Office of Inspector General, U.S. Department of Labor, Washington, DC 20210, or call (202) 219-4930.
This report reflects the findings of the Office of Inspector General
at the time that the audit was issued. More current information may be
available as a result of the resolution of this audit by the Department
of Labor program agency and the auditee. For further information concerning
the resolution of this report's findings, please contact the program agency
Report Title: Robinson Steel Construction Company (RSC)
Report Number: 18-94-015-03-370
Issue Date: July 14, 1994
($64,341 Questioned)
RSC is a for-profit private company that was awarded a fixed-price contract to provide heating, fire alarm and egress improvements at the St. Louis Job Corps Center. The contract was terminated for the convenience of the Government and RSC, with its two subcontractors, proposed a settlement of $261,677. The OIG performed an agreed-upon-procedures review to assist the Contracting Officer (CO) in arriving at an equitable settlement of the terminated contract.
OIG questioned $29,129 of the $188,566 proposed for direct termination costs. We found incorrect indirect cost rate calculations by RSC's two subcontractors, incorrect charging of supervisor's labor costs, and inappropriate charging of interest on an alleged late payment by the Government.
OIG also question $35,212 of the $54,254 claimed for settlement expenses. We found that the project manager and three secretaries proposed more hours than what was recorded on their timesheets; suspension overhead was claimed for a period in which the suspension order stated there would be no additional cost to the Government; costs were proposed in excess of what was paid and for training that had nothing to do with the terminated contract; and one of the subcontractors' claimed time charge as settlement expenses was excessive.
OIG also found $8,712 in claims for supplies (and related general and
administrative expenses) for which we were unable to verify whether or
not the items were actually used at the job site. The CO issued the report
to the contractor; however, the CO has not received a response. The CO
is writing to the contractor giving him an additional 30 days to respond
before he makes a final decision.